How to create the dependency fast in Gantt chart view?

Last Updated: Dec 23, 2015 05:16PM HKT
From the instructions of the TaskInfo in the help file, you should have known how to create dependency in the Taskinfo view.

Please review the steps to create a dependency in the TaskInfo view.

  1. Open the TaskInfo view from View menu,
  2. Select task A,
  3. Scroll down in TaskInfo view to Predecessors field and click the Plus button,
  4. Choose task B in the coming dependency dialog,
  5. Select Dependency type,
    • Finish to Start, Task A can't be started until Task B is finished.
    • Start to Finish, Task A can't be finished until Task B is started.
    • Start to Start, Task A can't be started until Task B is started.
    • Finish to Finish, Task A can't be finished until Task B is finished.
  6. Click Ok to finish.

Here, you can learn how to create dependency in the Gantt chart view directly. 


support2@xmind.org
http://assets3.desk.com/
false
desk
Loading
seconds ago
a minute ago
minutes ago
an hour ago
hours ago
a day ago
days ago
about
false
Invalid characters found
/customer/en/portal/articles/autocomplete